India's largest publicly disclosed battery-storage EPC order this year went to a company that does not manufacture cells.
On 16 November, NTPC Green Energy handed Pace Digitek a ₹2,691 crore contract for 600 MW / 1,800 MWh of storage at the Khavda solar park in Gujarat. Pace is a Bengaluru infrastructure firm that builds telecom power systems and, through its Lineage Power subsidiary, containerised storage racks. The filing names no supplier for the cells inside those racks.
That gap between the headline and the hardware is the story. India has spent two years arguing about who manufactures battery cells. Its gigawatt-hour-scale storage awards are being decided on civil works, grid integration, fifteen years of maintenance and a local-content clause.
It places 1.8 GWh of Indian storage demand with a balance-of-plant contractor; Pace's wider 6.62 GWh portfolio follows the same pattern.
What the ₹2,691 crore buys, and what it leaves out, matters more than the headline value.
The price reflects the scope
₹2,691 crore over 1,800 MWh works out to about ₹1.49 crore per MWh including GST. Strip the 18% tax and it lands near ₹12,700 per kWh, or roughly $135 at ₹94 to the dollar.
BloombergNEF's 2025 survey put the global average turnkey system price at $117 per kWh, with China at $73, Europe at $177 and the United States at $219. Those figures cover the battery rack, power conversion and energy management. They exclude EPC, grid connection and maintenance. Pace's number includes all three, plus a decade and a half of service.
On a like-for-like reading, the Indian price looks unremarkable. Using it as a cost signal for Indian storage would be misleading.
Implied contract price, Khavda Cluster-01
₹2,691 crore for 1,800 MWh of storage with EPC and 15-year O&M. Scope differs from turnkey battery benchmarks. · Pace Digitek filing, November 2026
Pace's own October 2025 SECI award offers a cleaner comparison. That contract was ₹1,159.31 crore including GST for a 600 MW / 1,200 MWh DC package with ten years of service, about ₹0.97 crore per MWh. The NTPC order is roughly 55% higher per MWh.
The scope, the year and the site all differ, so the gap tracks scope and timing. A storage headline means little until you know whether it covers the DC block alone or a full construction wrap. Much of the coverage of this order skipped that step.
An EPC wrap and a fifteen-year annuity
The scope is unusually wide for an Indian storage award. Pace is responsible for system supply, integration, installation, testing, commissioning, civil works and operations for fifteen years. Each block is 300 MW / 900 MWh. Together they form Cluster-01 of a 3,300 MWh programme at NTPC Renewable Energy's Khavda plant.
Completion is scheduled for September 2027.
On the company's numbers, cumulative FY2027 order inflows have reached ₹5,129 crore and the executable order book stands at ₹13,427 crore. Its consolidated storage portfolio is 6.62 GWh across EPC and build-own-operate models. That mix is the part worth studying.
| Parameter | Khavda (NTPC Green) | Delhi (BSES Rajdhani) |
|---|---|---|
| Model | EPC + 15-year O&M | BOOT, 12 years |
| Capacity | 600 MW / 1,800 MWh | 57.5 MW / 115 MWh |
| Value | ₹2,691 crore incl. GST | ₹179.4 crore project cost |
| Revenue shape | Construction margin + O&M fee | ₹47.05 lakh per MW per year, about ₹27.1 crore annually |
| Timeline | Complete by September 2027 | Seven months from LoI |
Pace Digitek disclosures, October–November 2026
The two contracts represent different businesses. Khavda is a construction job with a long service tail. Delhi is a small annuity: a fixed capacity tariff, paid yearly against a 115 MWh asset Pace will own for twelve years.
Venugopalrao Maddisetty, Pace's chairman and managing director, framed the win as proof of manufacturing and execution depth. "Winning this landmark BESS order is a validation of Pace Digitek's manufacturing scale, engineering depth and project execution capabilities," he said in the company's release.
As a Class-I Local Supplier under domestic value addition guidelines, this award highlights the crucial role of local content and domestic manufacturing in advancing India's energy storage goals.— Venugopalrao Maddisetty, Chairman & Managing Director, Pace Digitek
The mechanism he describes is doing real work in this award.
Local content is doing the choosing
Class-I Local Supplier status requires at least 50% of the value of goods, services and works to be domestic. Pace says that criterion was important in winning. It also says it has 5 GWh of operational domestic storage manufacturing capacity, an in-house container fabrication facility, and a plan to reach 10 GWh by the third quarter of FY2027.
Then there is the money behind the demand. On 4 November, the Union Cabinet approved a ₹14,500 crore viability gap funding scheme covering 92 GWh of grid-scale storage between FY2026-27 and FY2030-31. Of that, 60 GWh is pumped hydro, 30 GWh is batteries and 2 GWh is alternative technologies. Allocation runs through tariff-based competitive bidding, and the BESS projects carry a minimum 40% domestic content requirement.
As we wrote in our November piece on India's 40% storage rule, the rule is reshaping who can bid before it reshapes what gets built.
Here is where we part company with the bullish read. On their own, local content rules add assembly capacity and a paper trail; cell capacity requires separate investment. Pace's announcement names no cell supplier, and that omission is load-bearing: it decides how much of the 40% domestic content is real value addition and how much is imported cells in locally welded boxes.
The scheme doubles as industrial policy. Investors underwriting these awards are betting on domestic assembly economics as much as on storage demand.
Three hours is the number that decides the design
The block arithmetic defines the design: 900 MWh behind 300 MW is three hours of duration. The system targets evening peaks, moving midday solar into the hours when the grid actually strains. Seasonal shifting would need far more energy per megawatt.
Three hours changes everything downstream. It sets the augmentation strategy, because a three-hour system cycles hard and loses usable capacity faster than a two-hour one that sits idle most days. It sets the O&M contract, which is why fifteen years of service is bundled into the award. And it sets the warranty arithmetic that nobody publishes: throughput guarantees, state-of-health floors, and who eats the degradation when the asset is still cycling in year twelve.
The same number explains the shape of the national programme. Of the 92 GWh covered by the new viability gap funding scheme, 60 GWh is pumped hydro and 30 GWh is batteries. Batteries are faster to build and easier to site; pumped hydro offers longer duration. The government is buying both because three-hour batteries cannot cover a two-day wind drought, and pumped hydro cannot be built beside a substation in eighteen months.
This is the part of the Khavda award that will age well or badly. A 600 MW / 1,800 MWh system is a large bet that Gujarat's grid constraint is daily. If that assumption holds, Pace is building exactly the right asset. If the constraint turns out to be multi-day, the site has 1,800 MWh of the wrong duration and a fifteen-year service contract attached to it.
We lean toward the daily read. The procurement pipeline is being built around evening peaks, and the BESS tranche inside the VGF scheme is calibrated to hours. The call rests on grid physics and the shape of procurement.
What September 2027 will tell us
About ten months separate the award from the completion date. In that window Pace has to deliver 1,800 MWh across two blocks, on a site that already carries one of the world's largest solar builds. The schedule is tight for a first cluster of this size.
The remaining 1,500 MWh of the 3,300 MWh programme has not been awarded. If Cluster-01 lands on time, the next tranche follows quickly. If it slips, the schedule becomes the argument against the whole procurement model.
Cell supplier disclosure, which determines the real domestic value share.
September 2027 commissioning, which sets the pace for the remaining 1,500 MWh.
Per-MWh pricing on the next tranche, which will show whether ₹1.49 crore was a scope artefact or the new floor.
Pace closed 9.42% higher at ₹172.5 on the day of the award.
The move priced the order book. The cell question, the ten-month schedule and the sourcing of the most expensive component inside the system remain open.